To sort the columns please click on a column header.
Accessibility Project for Classrooms and Labs (Counters, Tables, Desks, Chairs)Consolidated$0
Accommodation/Ergonomic Furniture & Equipment (Staff, Faculty and Administrators)Consolidated$0
ADA Transition PlanConsolidated$1,203
AV/Low TechFinancially Complete$43,456
BiologyConsolidated$0
Building 1500 RenovationFinancially Complete$1,174,660
Building 2500 ReroofFinancially Complete$969,180
Campus FountainsConsolidated$0
Campus Wide Building System & Infrastructure Repairs/UpgradesFinancially Complete$620,727
Central Campus Site ImprovementsFinancially Complete$9,809,110
Choral Rehearsal HallFinancially Complete$150,002
Classroom Furniture ReplacementFinancially Complete$35,717
Complete Lot 1HConsolidated$0
Computer Equipment (Carts, Monitors)Consolidated$0
Convert to Adaptive Learning CenterConsolidated$0
Dental Hygiene/Radiology RenovationFinancially Complete$254,814
DesktopsFinancially Complete$6,447,933
Environmental Impact ReportFinancially Complete$282,730
Expansion of VDI ServersConsolidated$0
Exterior LightingConsolidated$0
Exterior Painting & Bird RemediationFinancially Complete$621,983
Exterior SignageFinancially Complete$351,451
Faculty/Staff/Administrator Office Refresh (Furniture)Financially Complete$15,311
Fine Arts Scene ShopFinancially Complete$767,347
Fire Alarm System Replacement Phase IIIFinancially Complete$900,374
Fire Alarm System Replacements Phase IIFinancially Complete$1,576,697
Foothill ContingencyActive$0
ForumFinancially Complete$3,912,855
Furniture and Equipment (Excluding Tech Related Equipment) FoothillFinancially Complete$11,705,554
General ClassroomsConsolidated$0
General ClassroomsConsolidated$0
Group II EquipFinancially Complete$1,073,647
Install Photovoltaic Arrays - Campus WideFinancially Complete$11,738,853
Instructional Equipment for BH, FA & PE 18-19Financially Complete$146,942
Irrigation Pump ReplacementFinancially Complete$258,260
Japanese Cultural CenterFinancially Complete$120,234
LA Division Office /ClassroomsConsolidated$9,816
LA General ClassroomsFinancially Complete$3,064,580
Language LabConsolidated$0
Library & ISCFinancially Complete$15,131,676
Loop Road Lighting & SafetyConsolidated$11,033
Loop Road Re-Alignment & Pedestrian Safety ImprovConsolidated$186,997
Loop Road ResurfacingFinancially Complete$1,012,739
Lot 2 & 3 Security ImprovementsConsolidated$0
Lot 4Consolidated$0
Lot 6Consolidated$11,459
Mainline Irrigation - Phase IIFinancially Complete$158,942
Modernization of Administration Building & General ClassroomsFinancially Complete$7,132,515
Modernization of Building 5700Financially Complete$361,698
Modernization of Learning Support Center, Biology and General ClassroomsFinancially Complete$16,203,253
New Multi Media, Then RefreshFinancially Complete$4,039,132
Ornamental Horticulture & Veterinary Technology Demo.Financially Complete$182,567
Outdoor and Indoor Student Seating (PSEC Café, 5000, 5100, 5400, etc.)Financially Complete$13,440
Parking and CirculationFinancially Complete$13,468,168
PE ReroofingFinancially Complete$976,594
Pedestrian Bridge Lot 1Consolidated$0
Physical Education Lab SpaceFinancially Complete$1,512,408
Physical Sciences and Engineering CenterFinancially Complete$57,627,320
Print Shop and Plant Services FacilityFinancially Complete$287,833
PrintersFinancially Complete$82,325
Reconstruction of Stadium Bleachers & Press BoxFinancially Complete$1,816,465
Refresh Multi Media RoomsFinancially Complete$1,152,489
Renovate Existing FootbridgeFinancially Complete$253,693
Repair and Upgrade Miscellaneous ProjectsFinancially Complete$451,424
Replace Storm DrainsConsolidated$0
Replace WalkwaysConsolidated$106,320
Slurry Coat and Re-stripe Lots 2 & 3Consolidated$0
Small Capital Repairs - FoothillFinancially Complete$3,811,411
Smithwick TheaterFinancially Complete$4,139,185
Soccer and Softball ComplexFinancially Complete$4,077,771
Storage Bldg at Swim Pool AreaFinancially Complete$536,837
Sunnyvale Ed Center HVAC System Replacement and Classroom RenovationActive$5,698,420
Swing SpaceFinancially Complete$965,079
Tennis Court ImprovementsConsolidated$0
Tree Maintenance and ReplacementConsolidated$0
TV CenterConsolidated$0
Upgrade Doors and HardwareFinancially Complete$40,247
Utility and Technology InfrastructureFinancially Complete$8,515,900
Utility Lids - Phase IIFinancially Complete$572,116
Veterinary TechnologyConsolidated$0
Widen Access Road to PEConsolidated$0