Chabot-Las Positas Community College District

Measure A Bond ProgramProject List

Measure A projects grouped by location, with status and budget
ProjectStatusBudget
Chabot College
Administrative Swing SpaceProject 562232Active$300,000
Advanced Manufacturing, Applied Technologies and BusinessProject 562160Active$19,216,956
Athletic Fields - BaseballProject 562500Complete$12,544,400
Athletic Fields - Football, Bleachers & PressboxProject 562501Active$25,237,500
Biology / Faculty Building 2100 Phase 2 (STEM Complex)Project 562210Active$58,328,664
Biology Building Phase 1Project 562315Complete$6,630,912
Building 3000 Reconstruction (state & district matching funds)Project 562320Active$18,566,633
Campus Infrastructure - Electrical PowerProject 562611Complete$384,126
Campus Infrastructure - Fire Water LoopProject 562612Complete$95,392
Campus Repairs & Small ProjectsProject 562520Active$993,391
Campus SafetyProject 562234Active$300,000
Campus Safety-Emergency Call Station ProjectProject 562603Complete$772,353
Campus Safety-Security Management SystemProject 562604Complete$2,256,422
Campus SecurityProject 562600Complete$1,229,409
Campus Security Phase 2Project 562605Pending$750,000
CC Project & Construction ManagementProject 562560Active$6,000,000
Classroom / Lab Equipment & Library MaterialsProject 562540Active$30,000,000
College CenterProject 562230Active$104,160,972
CS - Campus Fire Alarm / Public Address UpgradeProject 562601Complete$2,605,134
CS - Campuswide LED LightingProject 562602Complete$190,900
Demolish Bldg 100Project 562109Pending$412,304
Demolish Bldg 200Project 562209Consolidated$0
Demolish Bldg 2300Project 562239Pending$508,616
Demolish Bldg 2400 and Bldg 3800Project 562249Active$3,223,600
Early Childhood Lab School & PlayyardProject 562370Active$5,347,126
Event Center/Campus Safety Renovation Bldg 3800Project 562380Cancelled$1,025,541
Fire Technology - Hayward Training FacilityProject 562510Complete$18,347,749
Library & Learning Connection Building 100Project 562100Financially Complete$95,027,848
Mohr Fry Property AcquisitionProject 562551Complete$8,400,000
Mohr Fry Property Stabilization FundProject 562552Active$1,300,000
MPOE Project - Building 300Project 562300Complete$2,421,693
Parking and Pathways - Lots G, E & FProject 562610Complete$878,248
Property AcquisitionProject 562550Financially Complete$600,000
ReprographicsProject 562236Active$300,000
STEM CourtyardProject 562211Active$4,417,313
Unallocated Bond for Future ProjectsProject 562699Board Approved$1,729,458
Chabot College subtotal$434,502,661
Las Positas College
1900 Furniture/Storage RenovationProject 563706Active$324,957
Academic Support & Offices B2100Project 563700Closeout$72,350,246
Administrative Office 1690Project 563805Complete$697,670
Agricultural Sciences - HorticultureProject 563810Complete$7,335,737
Agricultural Sciences - ViticultureProject 563811Closeout$11,643,104
Athletic Acoustical ProjectProject 563743Closeout$154,826
Athletic FieldsProject 563740Closeout$31,206
Athletic Fields - Soccer Turf ReplacementProject 563741Complete$1,086,993
Athletic Outdoor CourtsProject 563742Active$18,047,992
AV Upgrades B2420Project 563701Complete$1,394,615
B100 Portable Removal and RenovationProject 563702Complete$2,352,835
B2401 Cultural CenterProject 563703Complete$1,196,013
Bldg 1300 RenovationProject 563717Active$3,769,201
Campus SecurityProject 563900Pending$1,017,386
Campus Security - Architectural Barriers 1600Project 563903Complete$738,093
Campus Security - Emergency Call StationsProject 563904Complete$794,052
Campus Security - Exterior LightingProject 563901Complete$451,810
Campus Security - LPR Security ProjectProject 563906Complete$10,395
Campus Security - Safe Schools LocksProject 563902Complete$756,777
Campus Security - Security Management SystemProject 563905Complete$1,338,934
Campus Vehicular CirculationProject 563730Pending$5,071,280
Central Utility Plant WallProject 563935Complete$357,519
Classroom / Lab AV & IT EquipmentProject 563831Active$8,000,000
Classroom / Lab Equipment & Library MaterialsProject 563830Active$31,400,000
EIR ServicesProject 563920Active$880,809
Guided Pathways ProjectProject 563704Active$2,297,941
Infrastructure - Campuswide Domestic WaterProject 563931Complete$976,992
Infrastructure - Exterior SignageProject 563934Active$1,908,200
Infrastructure - Hillside ErosionProject 563933Complete$605,049
Infrastructure - Verizon Tower ProjectProject 563932Financially Complete$1,702
Infrastructure HW/CW/ElectProject 563930Active$7,234,112
LPC Project & Construction ManagementProject 563860Active$6,400,000
Music Renovation ProjectProject 563716Active$4,623,378
Property AcquisitionProject 563850Financially Complete$519,191
Public Safety Complex/AMT ProjectProject 563715Complete$51,439,359
Small Capital ImprovementsProject 563705Active$1,304,698
STEAM - Science & Arts BuildingProject 563750Active$149,701,529
Temporary Relocatable Office ProjectProject 563800Complete$3,642,027
Unallocated Bond for Future ProjectsProject 563999Board Approved$13,786,818
Las Positas College subtotal$415,643,445
District & District-wide
2018 Facilities Master Plan UpdateProject 561090Complete$594,340
2024 Facilities Master Plan UpdateProject 561091Active$750,000
Building 3000 Reconstruction - Chabot CollegeProject 561050Consolidated$77,278
Deferred Maint. & Repairs; Roofs, HVAC, Small Projects - Chabot CollegeProject 561021Financially Complete$1,005,264
Deferred Maint. & Repairs; Roofs, HVAC, Small Projects - Las Positas CollegeProject 561022Closeout$1,000,000
Deferred Maint. & Repairs; Roofs, HVAC, Small Projects (TCO)Project 561020Active$13,944,736
District Contingency Fund 5%Project 561099Board Approved$8,037,500
District Office Security EquipmentProject 561027Complete$153,260
Dublin Education Center / Contract Ed / TVOSProject 561040Complete$401,701
Dublin Education Center Phase 3Project 561042Complete$3,579
Energy ProjectsProject 561060Active$5,986,292
Information Technology & Tech UpgradesProject 561010Active$32,218,900
IT Classroom, Lab Equipment - Chabot CollegeProject 561011Active$20,592,700
IT Classroom, Lab Equipment - Las Positas CollegeProject 561012Active$16,320,700
M&O EquipmentProject 561025Active$1,800,000
Program Level Services, DistrictProject 561030Active$30,000,000
Small Projects & EquipmentProject 561043Active$150,000
District & District-wide subtotal$133,036,250
Total$983,182,356