Administration HVAC Upgrades
Last updated on April 03, 2026
PROJECT DESCRIPTION:
Upgrade existing HVAC units with controls, variable refrigerant flow, and split systems for improved comfort in the building.
STATUS:
Active
| BUDGET:
$1,550,000
PHASE:
Construction
|
PROJECT TEAM:
Architect
Cypress Engineering Group
Contractor
ACCO Engineered Systems
District Lead
Monterey Peninsula College
Project Manager
Ausonio Incorporated
Project Status
Original project scope is substantially complete.
Last 90 Days
Punch walk completed on project. Commissioning took place, awaiting initial report.
Next 90 Days
Looking into air balancing the entire building, getting all air ducts cleaned and obtaining a quote to replace the boiler.
PROJECT SCHEDULE:
Bid Phase Start
April 2025 - May 2025
Construction Start
December 2025 - March 2026
Closeout
March 2026 - May 2026