Welcome Center
Last updated on May 06, 2026
PROJECT DESCRIPTION:
Demolish existing General Classroom /Welcome Center dilapidated residential style army building. Design and construct new Campus Welcome Center to serve as the main hub for student programs at the Monterey Campus. New building program will include added square footage for additional student programs such as Umoja, El Centro, Women's Center, LGBTQIA+, Career & Transfer Center, etc. along with nap pods, quiet room for meditation/prayer, outdoor lounge area, gender-neutral bathrooms/shower, private lactation room, and changing table.
STATUS:
Active
| BUDGET:
$18,000,000
PHASE:
Construction
|
PROJECT TEAM:
Architect
Anderson Brule Architects
Contractor
Tombleson, Inc
District Lead
Monterey Peninsula College
Project Manager
Brailsford and Dunlavey Inc
Project Status
On schedule
Last 90 Days
Interior sheetrock was installed and painting has begun. FF&E has been ordered.
Next 90 Days
Interior painting, tilework and millwork will continue. Exterior cladding continuing to be installed.
PROJECT SCHEDULE:
Pre-Design
November 2022 - May 2023
Preliminary Plans
May 2023 - December 2023
Working Drawings
December 2023 - April 2024
DSA Review
May 2024
Bidding
November 2024 - January 2025
Construction
June 2025 - July 2026
Close Out
August 2026 - September 2026