Welcome Center
Last updated on May 06, 2026

PROJECT DESCRIPTION:
Demolish existing General Classroom /Welcome Center dilapidated residential style army building. Design and construct new Campus Welcome Center to serve as the main hub for student programs at the Monterey Campus. New building program will include added square footage for additional student programs such as Umoja, El Centro, Women's Center, LGBTQIA+, Career & Transfer Center, etc. along with nap pods, quiet room for meditation/prayer, outdoor lounge area, gender-neutral bathrooms/shower, private lactation room, and changing table.



STATUS:   Active

BUDGET:    $18,000,000      PHASE:    Construction

PROJECT TEAM:
Architect Anderson Brule Architects
Contractor Tombleson, Inc
District Lead Monterey Peninsula College
Project Manager Brailsford and Dunlavey Inc

Project Status

On schedule


Last 90 Days

Interior sheetrock was installed and painting has begun. FF&E has been ordered.


Next 90 Days

Interior painting, tilework and millwork will continue. Exterior cladding continuing to be installed.



PROJECT SCHEDULE:

Pre-Design November 2022 - May 2023
Preliminary Plans May 2023 - December 2023
Working Drawings December 2023 - April 2024
DSA Review May 2024
Bidding November 2024 - January 2025
Construction June 2025 - July 2026
Close Out August 2026 - September 2026