Music Building
Last updated on August 19, 2026
PROJECT DESCRIPTION:
New construction of Music Building to include a large choral and recital classroom space, practice rooms, control booth, staff offices, instrumental classrooms, and support spaces.
Live Construction Camera
STATUS:
Active
| BUDGET:
$17,500,000
PHASE:
Construction
|
PROJECT TEAM:
Architect
19 Six Architects
Contractor
SC Builders, Inc
District Lead
Monterey Peninsula College
Project Manager
Brailsford and Dunlavey Inc
Project Status
Project on track for Substantial completion on 12/31/2026
Last 90 Days
Underground, Utilities and Foundation forms completed. 320 yards of concrete needed for foundations
Next 90 Days
Framing of building structure to start in spring of 2026
PROJECT SCHEDULE:
Design
December 2022 - July 2024
DSA Review
September 2024 - December 2024
Bidding
May 2025 - July 2025
Construction Start
November 2025
Close Out
January 2027 - February 2027