Music Building
Last updated on August 19, 2026

PROJECT DESCRIPTION:
New construction of Music Building to include a large choral and recital classroom space, practice rooms, control booth, staff offices, instrumental classrooms, and support spaces.

Live Construction Camera

STATUS:   Active

BUDGET:    $17,500,000      PHASE:    Construction

PROJECT TEAM:
Architect 19 Six Architects
Contractor SC Builders, Inc
District Lead Monterey Peninsula College
Project Manager Brailsford and Dunlavey Inc

Project Status

Project on track for Substantial completion on 12/31/2026


Last 90 Days

Underground, Utilities and Foundation forms completed. 320 yards of concrete needed for foundations


Next 90 Days

Framing of building structure to start in spring of 2026



PROJECT SCHEDULE:

Design December 2022 - July 2024
DSA Review September 2024 - December 2024
Bidding May 2025 - July 2025
Construction Start November 2025
Close Out January 2027 - February 2027