Renovate Restrooms in S2, S6 & L5
Last updated on July 11, 2024
PROJECT DESCRIPTION:
Renovate S2, S6, & L5 restrooms to gender neutral at De Anza College.
STATUS:
Active
BUDGET:
PHASE:
ARCHITECT:
CONTRACTOR:
$3,403,900
Design
Noll And Tam Architects
N/A
UPCOMING ACTIVITY:
In Design
Currently with DSA for document review and approval
Receive DSA comments - estimated Mid October
DSA Backcheck comments and responses back to DSA - estimated Mid October thru Mid November
DSA Sign-off is estimated for early December
Procurement estimated December 2024 thru early April 2025
Construction is estimated to begin April 2025
PROJECT SCHEDULE:
Design Phase
January 2023 - December 2024
DSA
June 2024 - December 2024
Procurement
December 2024 - April 2025
Construction
April 2025
Closeout
December 2025 - June 2026