Last updated on July 11, 2024

PROJECT DESCRIPTION:
Renovate S2, S6, & L5 restrooms to gender neutral at De Anza College.

STATUS:   Active

BUDGET: PHASE: ARCHITECT: CONTRACTOR:
$3,403,900
Design
Noll And Tam Architects
N/A

UPCOMING ACTIVITY:
  • In Design
  • Currently with DSA for document review and approval
  • Receive DSA comments - estimated Mid October
  • DSA Backcheck comments and responses back to DSA - estimated Mid October thru Mid November
  • DSA Sign-off is estimated for early December
  • Procurement estimated December 2024 thru early April 2025
  • Construction is estimated to begin April 2025



PROJECT SCHEDULE:
Design Phase January 2023 - December 2024
DSA June 2024 - December 2024
Procurement December 2024 - April 2025
Construction April 2025
Closeout December 2025 - June 2026