Renovate Football Stadium East Bleachers
Last updated on March 25, 2024

PROJECT DESCRIPTION:
Renovate football field/stadium eastside seating for accessibility compliance (ADA) improvements.

STATUS:   Active

BUDGET: PHASE: ARCHITECT: CONTRACTOR:
$1,376,600
Construction
Loving Campos Associates, Architects Inc
Guerra Construction Group

UPCOMING ACTIVITY:
Construction began 3/4/24 and has continued to progress.


PROJECT SCHEDULE:
Procurement October 2023 - January 2024
Construction March 2024 - August 2024
Closeout August 2024 - January 2025