Renovate Football Stadium East Bleachers
Last updated on July 11, 2024
PROJECT DESCRIPTION:
Renovate football field/stadium eastside seating for accessibility compliance (ADA) improvements.
STATUS:
Active
BUDGET:
PHASE:
ARCHITECT:
CONTRACTOR:
$1,376,600
Construction
Loving Campos Associates, Architects Inc
Guerra Construction Group
UPCOMING ACTIVITY:
Punch list to be completed.
Closeout of Project.
PROJECT SCHEDULE:
Procurement
October 2023 - January 2024
Construction
March 2024 - July 2024
Closeout
July 2024 - January 2025