Upgrade ADA Pathways at Buildings 8200 and 8600
Last updated on July 18, 2024
PROJECT DESCRIPTION:
Addition of an accessibility compliant (ADA) pathway between buildings 8200 and 8600 and outdoor classroom space at Lower Campus facility area.
STATUS:
Active
BUDGET:
PHASE:
ARCHITECT:
CONTRACTOR:
$1,693,532
Construction
Loving Campos Associates, Architects Inc
Rodan Builders Inc
UPCOMING ACTIVITY:
Construction will be continued with the following activities:
Grading
Excavation and Soil Removal
Drain rock installation
Plumbing and electrical pipe installation
Irrigation installation
Concrete pour on sidewalk and ramps
Electrical light bollard installation
Planting and mulching
Site furniture and signage installation
Paving and striping
PROJECT SCHEDULE:
Procurement
December 2023 - March 2024
Construction
March 2024 - October 2024
Closeout
October 2024 - February 2025