Upgrade Restrooms to All Gender
Last updated on July 11, 2024
PROJECT DESCRIPTION:
Upgrade and renovate restroom facilities, includes gender neutral additions and accessibility compliance (ADA) improvements to support college's equity initiative.
STATUS:
Active
BUDGET: |
PHASE: |
ARCHITECT: |
CONTRACTOR: |
$1,861,866
|
Construction
|
Steinberg Hart
|
Sandh Construction, Inc. |
UPCOMING ACTIVITY:
Completing the following scopes:
- Fire sprinkler system
- Ceiling framing
- fire alarm system
- HVAC
- Painting
- Wall tiling
- Resinous flooring
- Toilet compartments
- Plumbing fixtures
- Light fixtures
PROJECT SCHEDULE:
Procurement
September 2023 - January 2024
Construction
March 2024 - October 2024
Closeout
October 2024 - December 2024