Physical Education Complex Renovation
Last updated on April 27, 2026

PROJECT DESCRIPTION:
Physical Education Complex improvements and modernization to enhance the student learning environment and improve student success including temporary user relocation to swing space.

STATUS:   Active

BUDGET:    $11,312,229      PHASE:    Design



Upcoming Activity

Working Drawings (Construction Documents Phase)



PROJECT SCHEDULE:

Start Preliminary Plans August 2025 - February 2026
Start Working Drawings March 2026 - July 2026
Complete Working Drawings September 2026 - September 2026