Physical Education Complex Renovation
Last updated on April 27, 2026
PROJECT DESCRIPTION:
Physical Education Complex improvements and modernization to enhance the student learning environment and improve student success including temporary user relocation to swing space.
STATUS:
Active
| BUDGET:
$11,312,229
PHASE:
Design
|
Upcoming Activity
Working Drawings (Construction Documents Phase)
PROJECT SCHEDULE:
Start Preliminary Plans
August 2025 - February 2026
Start Working Drawings
March 2026 - July 2026
Complete Working Drawings
September 2026 - September 2026