Upgrade Fire Alarms and Suppression Systems
Last updated on January 31, 2024

PROJECT DESCRIPTION:
Fire alarm and fire suppression system modification and upgrades to meet current code compliance (panels, distribution, electrical, piping, etc.).

STATUS:   Active

BUDGET: PHASE: ARCHITECT: CONTRACTOR:
$4,818,400
Design
Jensen Hughes Inc
N/A

UPCOMING ACTIVITY:
Pathway investigation - proof/rod potential pathways.  Remove existing unused cabling from conduits, verify potential pathways are useable and pole mule tape in conduits to be used in fire alarm project.


PROJECT SCHEDULE:
Programming - Survey Program Analysis Pathway Investigations June 2022 - February 2024
Procurement Pathway Investigation July 2023 - February 2024
Construction Pathway Investigations March 2024 - April 2024
District Review Comments/Approval for Submission to DSA November 2024