Back to list
Upgrade Fire Alarms and Suppression Systems
Last updated on January 31, 2024
PROJECT DESCRIPTION:
Fire alarm and fire suppression system modification and upgrades to meet current code compliance (panels, distribution, electrical, piping, etc.).
STATUS:
Active
BUDGET:
PHASE:
ARCHITECT:
CONTRACTOR:
$4,818,400
Design
Jensen Hughes Inc
N/A
UPCOMING ACTIVITY:
Pathway investigation - proof/rod potential pathways. Remove existing unused cabling from conduits, verify potential pathways are useable and pole mule tape in conduits to be used in fire alarm project.
PROJECT SCHEDULE:
Programming - Survey Program Analysis Pathway Investigations
June 2022 - February 2024
Procurement Pathway Investigation
July 2023 - February 2024
Construction Pathway Investigations
March 2024 - April 2024
District Review Comments/Approval for Submission to DSA
November 2024